4 ms·
Not uncommon, there was a ton of it after 2008. For steel and concrete highrises, it's not a huge deal. As matter of fact developers build these things in para
by pxmpxm 3y ago
Not uncommon, there was a ton of it after 2008. For steel and concrete highrises, it's not a huge deal.
As matter of fact developers build these things in parallel, lower levels are getting interiors while upper floors are still open to elements concrete and middle is getting framed out for interior. Kinda interesting to see a tower that's getting washers/dryers and exterior windows installed at the same time...
https://www.wsj.com/articles/SB10001424052748704226004575262580613845118 https://www.wsj.com/articles/SB10001424052748704226004575262...
- zamfi 3y agoSure, but I think this is a bit apples-and-oranges. 2008-era restarts were overwhelmingly completed by the original owners, with < 2y pauses, and most were pretty small. We’ll just have to wait and see I guess!