2 ms·
I'm in the unfortunate position where I'm curious to learn why extrapolating from Georgia is flawed, while also not loving the idea of reading through a 30 page
by bitshiftfaced 3y ago
I'm in the unfortunate position where I'm curious to learn why extrapolating from Georgia is flawed, while also not loving the idea of reading through a 30 page technical document to find out why.
- JumpCrisscross 3y agoThey “experienced several one-time delays including redesign and reworks from the first application of 10CFR52 design certification process and insufficient engineering before start of the construction” [1]. If you’re building N of a kind, the N = 1 costs are almost always higher. We know these are possible with AP1000s because we can see the same cost curve in China, albeit shifted down due to lower labour costs. [1] Executive Summary