> That leaves you with 200A*240V=480kW You’re off by an order of magnitude: 200 * 240 = 48000 > If you're willing to pay, you can probably convince your utili
by quickthrowman 3y ago
> That leaves you with 200A*240V=480kW
You’re off by an order of magnitude: 200 * 240 = 48000
> If you're willing to pay, you can probably convince your utility to hook you up to three phase power, which is typically reserved for industrial use.
Three-phase power isn’t only for industrial use, (in the United States) small commercial buildings will have a 208v three-phase service drop and larger commercial buildings will have a 480v service drop, or 13.8kV medium voltage drop if it’s big enough. Large enough industrial customers will have dedicated substations.