It is quite possible to build save nuclear plants in a short time. Swedish Barsebäck and Oskarshamn took 5 years each, finnish Olkiluoto 1 started already after
by TheChaplain 3y ago
It is quite possible to build save nuclear plants in a short time. Swedish Barsebäck and Oskarshamn took 5 years each, finnish Olkiluoto 1 started already after 4 years. In the heavy bureaucratized Germany Unterweser took 6 years from first dig in the ground.
All these are from the 1970's, and now roughly 50 years later, our evolved technology and knowledge of nuclear technology and safety, should make it even faster and safer.
But funny enough it doesn't get faster. I have my suspicions why, but have not formulated my thoughts enough to blog about it.
- adrianN 3y agoA lot has to happen before you can break ground building a nuclear power plant. Pure construction time is not a good measure.