right, and then you get into effort vs duration game. so every task now takes 2 weeks duration because it will get approx 2 days of effort in that window. the
by steveBK123 3y ago
right, and then you get into effort vs duration game.
so every task now takes 2 weeks duration because it will get approx 2 days of effort in that window.
then the next side effect is any remotely challenging task gets avoided because the duration of a 1 week task becomes 5 weeks and.... forget it.
- em-bee 3y agovery true. but when you are in the situation with more projects than developers, each project will have to wait either way. can't get around that. it either takes 2 weeks because the developer works on multiple projects at the same time, or it takes 2 weeks because the project spends most of the time waiting in the queue. the end result is the same. so it really doesn't matter. the benefit if the queue system is that you get to focus on one project at a time. the benefit of the paralell system is that you don't waste waiting times that may occur when during the development you need something from someone else and have to wait for their response. which is better depends on the specific project and how the stakeholders communicate.