The problem is when a single methodology is seen as a silver bullet for all kinds of projects -- it almost never is. The benefit of "scrum" is that it splits t
by BerislavLopac 3y ago
The problem is when a single methodology is seen as a silver bullet for all kinds of projects -- it almost never is.
The benefit of "scrum" is that it splits the development into chunks of work that can be used when planning, which is why it is well suited when the majority of work consists of development and delivery of new features.
On the other hand, "kanban" works much better when the majority of work is maintenance, bug fixes, paying off of technical debt and only a limited amount of new development.
- rhaway84773 3y agoDoesn’t Kanban split development into chunks of work as well? The only difference between Kanban and scrum that I can see is that Kanban doesn’t insist on a 2 week sprint, although there’s no reason why you can’t adopt a Kanban system with a 2 week checkpoint and prediction window as well.
- pg_1234 3y agoKanban shows you where you are (how you use this info is up to you). Scrum shows you where you are and tries to predict where you'll be in 2 weeks. Where Scrum goes horribly wrong is when management tries to treat the 2 week prediction as a guarantee rather than a guess ... and to compound the problem imposes tougher predictions/deadlines to squeeze out more work. Whatever the stated intentions, in practice Scrum almost always goes bad in this way.