As far as I can tell there are two major problems with this. The first is that you can predict that there will be unforeseen problems, but not how many of them
by AnthonyMouse 3y ago
As far as I can tell there are two major problems with this.
The first is that you can predict that there will be unforeseen problems, but not how many of them nor how long each will take to resolve. The result is high variance. Then if the average such project takes 16 months, and you predict each such project will take 16 months, then some take 7 months and some take 17 months and some take 25 months and people get mad at you for underestimating some of them. But if you predict at the upper end of the range then people will get mad at you for giving 25 month estimates for projects that only take 16 months on average.
The second is that people know what the estimate is and work expands to fill all available time. When you know you have 16 months, you set a pace that will have the project finished in 16 months. Then in month 14 you encounter some unexpected problem that takes six months to resolve. If you'd found it in month 2 you'd have been fine, because you'd have cut some less critical features and spent the time on that, but now that's in the past and your project is five months late.
- Arrath 3y agoThe third major problem: Project Manager/Scheduler/Sales/Customer doing one/any/all of: not believing the input of the SME (you) when they ask for input developing the schedule, overpromising, expecting the world, or so many other problems. Too many times in my own field (heavy construction) the scheduler has asked me how long it will take to do a given task, and it is actually reasonably quantifiable to say "It will take my crew X days to move Y volume of material at Z/shift" only to be told "Well our proposal only allocated X-5 days and budgeted a Crew of <your chosen size - 4> for that task. Figure it out."