3 ms·
The major issue with nuclear power is and always has been costs are just too damn high. What nobody talks about is increasing the efficiency of coal power plan
by Retric 3y ago
The major issue with nuclear power is and always has been costs are just too damn high. What nobody talks about is increasing the efficiency of coal power plants significantly reduced their operating costs. The same was true of everything including hydro except nuclear which just kept getting more expensive compared to alternatives over time.
Coupling long plant lifespans with minimal growth in electricity demand for decades meant there was no incentives to build nuclear after it reached ~30% of total demand. It couldn’t pass that ~30% threshold because costs enter an exponential spiral of decreasing capacity factor meaning higher fees when it’s in operation.
PS: I say ~30% because the actual economics get really complicated that’s just what most countries seem to roughly settle on. Forecasting today out a full plants lifespan and I don’t think even 30% is still viable without massive subsidies.
- pfdietz 3y agoIt was actually natural gas fired plants that put the nails in the coffin for the "Nuclear Renaissance". The important fact: a combined cycle natural gas power plant has a capital cost of about $1/watt, with a thermal efficiency of about 60% (LHV). Vogtle 3/4 are something like $15/W. And natural gas on the Henry Hub is $2.28/million BTU right now (at 60% efficiency, that's a fuel cost of $.013/kWh).