“ The Public Interest Advocacy staff of the Georgia Public Service Commission warned back in 2008 that the costs could skyrocket. They advocated for a risk-shar
by theoldlove 3y ago
“ The Public Interest Advocacy staff of the Georgia Public Service Commission warned back in 2008 that the costs could skyrocket. They advocated for a risk-sharing mechanism to incentivize Georgia Power to keep the construction costs down and opposed plans to bill customers for the Vogtle construction while it was underway.
Both proposals failed. Thanks to a 2009 state law, Georgia Power ratepayers are billed a monthly Nuclear Construction Cost Recovery fee. They will begin paying an additional monthly charge when each of the new Plant Vogtle units come online.”
If I were a Georgia Power customer I’d be livid. Why on Earth should I be on the hook for cost overruns instead of the company building the thing?
- elif 3y agoGP customer here. They have a monopoly anyway, so they will recover costs one way or another anyway. Also, we pay some of the lowest energy rates in the country so there's not much to be mad about. Overnight I pay $0.01/kwh ($0.03 if you include fees). Lastly, why get mad when you can get solar.
- lotsofpulp 3y agoWow, I thought my $0.08/kWh in PNW was great.
- lftl 3y agoNote that elif said "overnight" rate. I'm pretty sure they're on the EV rate plan from GA Power[1]. You only get that rate at night, and you pay a pretty punitive $0.21/kwh for any peak usage. As they mentioned, that's a pretty solid number for the marginal rate you'll pay for an extra kwh, but there are a number of base fees tacked on to that. I'm not on the EV plan, but my average out the door winter final rate is about $0.13/kwh and my summer rate ends up being more like $0.17/kwh. [1] https://www.georgiapower.com/residential/billing-and-rate-plans/pricing-and-rate-plans/plug-in-ev.html https://www.georgiapower.com/residential/billing-and-rate-pl...
- lotsofpulp 3y agoOh, that makes more sense.
- hackernewds 3y agoStill great for charging your EV overnight
- tkanarsky 3y agoPff, your punitive 21¢/kWh is cheaper than our overnight 25¢/kWh or so in the Bay Area :P
- mcv 3y agoIs night time energy still cheaper than day time? I thought that with the rise of cheap solar, day time energy would have been cheaper by now.
- jandrese 3y agoThat also incentivizes home battery systems. Charge it up overnight and then use the battery power during peak times. It's a good deal for the power company if you do that too because it reduces amount of swing in the grid.
- willis936 3y agoJesus. I pay 28c/kWh + 8c/kWh delivery (and many other fees that add to another 7c/kWh).
- zbrozek 3y agoCalifornia costs are unhinged. I'm extremely excited to get my ducks in a row and move out.
- mcv 3y agoIf the US is so big on the free market, why are there monopolies everywhere? In Netherland I can choose who to buy my energy from (I buy mine from a company that provides only green energy).
- Georgelemental 3y agoThe entity responsible for these overruns is the US Nuclear Regulatory Commission. They are the ones who should lose funding!
- epistasis 3y agoIn what way? Be specific. I have never heard a single regulation that should change, and the AP1000 reactors at both Summer and Vogtle were approved under a new process pushed for by the nuclear industry. In truth, basic incompetence from design to EPC has caused these disasters. And it's not just the US NRC, it's happened in Europe with France's EPR, too. The NRC is a scapegoat for the incompetent, that don't want to look at the true sources of failure.
- evilos 3y agoHere's a specific complaint about the application of a new and unnecessary airplane strike rule to an already approved design: https://atomicinsights.com/nrcs-imposition-of-aircraft-impact-rule-played-a-major-role-in-vogtle-project-delays-and-vc-summer-failure/ https://atomicinsights.com/nrcs-imposition-of-aircraft-impac... Personally, I think what will happen is that other countries like China and South Korea will build lots and lots of NPPs cheaply and quickly and the US will only consider making changes to the way things are done after looking incredibly inept in comparison. The NRC is only one of many things that needs to change.
- philipkglass 3y agoThis doesn't explain why the Vogtle AP1000s had cost/schedule overruns. You can blame the NRC rules for adding complexity and cost but you can't blame the NRC for the nuclear industry's wildly over-optimistic estimates. According to that article, the airplane strike rule was added in 2009. The reactors began construction in 2013 with certain cost/schedule estimates. If the airplane strike rule significantly increased effort, that should have been accounted for before they actually started building. They had 4 years in advance to figure it out (or, if they couldn't figure it out in time, to postpone until they understood the consequences). After construction started the project kept slipping and costs kept going up for 10 years, despite the rules remaining the same since construction was actually under way.
- cpursley 3y agoIt's offset by the fact that high energy consumption industry is moving to Georgia in a big way. Battery plants, car manufacturers, mattress factories, all sorts of well paying non-service industry non college degree positions that make for a robust diverse economy. - https://www.georgiatrend.com/2023/03/29/2023-industry-outlook/ https://www.georgiatrend.com/2023/03/29/2023-industry-outloo... - https://www.selectgeorgia.com/discover-georgia/industries/ https://www.selectgeorgia.com/discover-georgia/industries/ - https://gov.georgia.gov/press-releases/2023-01-19/gov-kemp-key-industries-sustain-momentum-states-economic-development https://gov.georgia.gov/press-releases/2023-01-19/gov-kemp-k...