Just off the top of my head: - Longer permitting delays, including structural engineering work and electrical design work to tie into the existing warehouse el
by emtel 3y ago
Just off the top of my head:
- Longer permitting delays, including structural engineering work and electrical design work to tie into the existing warehouse electrical system.
- Need to rent cranes or lifts to hoist equipment onto roof.
- Warehouses may need to be partially closed while roof work is being done, for safety.
- Probably need to do roof penetrations for fasteners and ensure they are sealed.
- Likely increase in worker death and injury rate from working on roofs instead of the ground.