The goal of estimating is to know how long it will take to complete a given task. A successful estimating methodology ought to provide this. I am not convinced
by lumb63 3y ago
The goal of estimating is to know how long it will take to complete a given task. A successful estimating methodology ought to provide this. I am not convinced the method you outline does provide this.
First, I would be interested to see any data you have supporting the idea that “humans are much better at estimating relative effort than average time”. My own experience is humans have biases toward optimism or pessimism and are poor estimators of the magnitude of risk, but I’ll ignore that for the moment and accept the premise as true.
The other underlying premise of your method is that velocity is a random variable about this perfect prediction with a known distribution, such that via the law of large numbers, over a large number of sprints, the average velocity can be known with high accuracy. I see a few issues with this.
One issue is that velocity is not static. Velocity changes with team morale and how interesting or motivating the task is. It changes with how well engineers are suited to a task. It changes with organizational changes, the addition of new team members, the loss of old ones, the work environment, etc. I don’t buy that these are small factors that average out over the long run, either, since my experience leads me to believe they don’t. A poor work environment or coworkers leaving the team or low morale usually are harbingers of bad things to come, and, opposite, a growing team working usually has exciting challenges, morale is usually high, etc. My experience hasn’t shown a mixed bag of equal good and bad, but instead two divergent sets.
Even if velocity were static, the other issue is the distribution is unknown. Sometimes teams have bad weeks, and sometimes they have good ones. Sometimes something catastrophic happens in the organization and a dozen engineers are twiddling their thumbs or are thrown into some task they did not foresee. Sometimes things go unexpectedly well. A priori, there’s no way of knowing what a particular team tends to, or if that trend will continue. One could try to measure it, but my experience has been that something that was supposed to be static will change long before a sufficient amount of data could be collected to be meaningful.
Even if you knew the exact distribution you’d encounter, the final problem that remains is that projects aren’t infinitely long. There aren’t a million sprints to smooth things out. There will be variation in the outcome.
I guess what I’m saying is, estimates are estimates. Why systematize their creation when they will ultimately be wrong, and creating them is so costly? I could understand having a system if it were low-overhead, but my experience with a system similar to what you’re describing was anything but that.