Well no, and rocket science works which is one difference. I've been through all this with multiple teams/companies and I wasn't always even opposed to the ide
by sanitycheck 3y ago
Well no, and rocket science works which is one difference.
I've been through all this with multiple teams/companies and I wasn't always even opposed to the idea! In the end all point-based estimates seem to do is add more ways to be wrong.
Humans are actually pretty good at estimating absolute time if they've had some practice. After the first few times you estimate a day and it takes a week, you realise you're an optimist and you should compensate for that. It seems the wrong conclusion to draw would be "oh well it's impossible, I should use made-up units instead", just get better at it. There was a time I was mostly doing fixed-price work, nobody would have accepted points in a quote and nobody would pay me per point.
Consistency in unit sizes is basically impossible, from what I've seen - unless there's an unspoken but commonly understood translation to units of time.
Project managers who try to size sprints in points tend to eventually give up, after finding that the the actual effort taken varies so wildly between sprints. (I also tend to think sprints suck, and Kanban is the way to go for agile - but that's another topic.)
- chasd00 3y ago> There was a time I was mostly doing fixed-price work, nobody would have accepted points in a quote and nobody would pay me per point. I've done that too and fixed-price work is like handling dynamite. I've always felt it was good for new grads to spend a couple years in small, eat-what-you-kill, consulting shops to understand the business of software development better. After that, then go to megacorp/faang or whatever but the lessons learned in a small consultancy will help you see the forest through the trees.
- burnished 3y agoMy team does point based estimation and I like it. The points are useful for getting an idea of how much stuff to work on in a sprint and a measure for how much room we need to leave in for the inevitable and consistent problems that we have to pick up mid sprint. The real benefit imo is that it is a good shorthand during estimation that reveals misunderstandings or flaws in a ticket. Everyone pointing a ticket at a 2 is whatever, literally any time spent discussing if it is a 2 vs a 3 drains my vitality, but every time there is a big outlier or bimodal distribution we get a lot of value from talking it out. I think what points gets you here over hours is that it focuses on the task at hand. I think a time centric approach requires your estimates to be more like 'X hours for John, Y hours for Shirley'. I'm not touching your points about how there are other contexts where it doesn't make sense to do this, or the absurdity inherent in pretending that they don't still boil down to time in a meaningful sense because I agree with them.