From the Rogers report [1]: Engineers at Thiokol also were increasingly concerned about the problem. On July 22, 1985, Roger Boisjoly of the structures section
by raphman 15y ago
From the Rogers report [1]:
Engineers at Thiokol also were increasingly concerned about the problem. On July 22, 1985, Roger Boisjoly of the structures section wrote a memorandum predicting NASA might give the motor contract to a competitor or there might be a flight failure if Thiokol did not come up with a timely solution.
Nine days later (July 31) Boisjoly wrote another memorandum titled "O-ring Erosion/Potential Failure Criticality" to R. K. Lund, Thiokol's Vice President of Engineering:
"The mistakenly accepted position on the joint problem was to fly without fear of failure and to run a series of design evaluations which would ultimately lead to a solution or at least a significant reduction of the erosion problem. This position is now changed as a result of the [51-B] nozzle joint erosion which eroded a secondary O-ring with the primary O-ring never sealing. If the same scenario should occur in a field joint (and it could), then it is a jump ball whether as to the success or failure of the joint because the secondary O-ring cannot respond to the clevis opening rate and may not be capable of pressurization. The result would be a catastrophe of the highest order-loss of human life."
Boisjoly recommended setting up a team to solve the O-ring problem, and concluded by stating:
"It is my honest and very real fear that if we do not take immediate action to dedicate a team to solve the problem, with the field joint having the number one priority, then we stand in jeopardy of losing a flight along with all the launch pad facilities."
[1] http://history.nasa.gov/rogersrep/v1ch6.htm http://history.nasa.gov/rogersrep/v1ch6.htm
- lutorm 15y agoBoisjoly recommended setting up a team to solve the O-ring problem And there was a team working on it. IIRC, a redesign of the joint was being worked on. But no one suggested, before the evening before the launch, that launches should be stopped until the redesign was completed.
- ScottBurson 15y agoNo. But they did suggest that launching in unusually cold weather was a very bad idea.