“The expensive part of nuclear power is building + certifying” Unfortunately this is not the case, decommissioning for example is extremely expensive though ca
by Retric 4y ago
“The expensive part of nuclear power is building + certifying”
Unfortunately this is not the case, decommissioning for example is extremely expensive though can be deferred for years. Nuclear requires a large and expensive workforce, expensive maintenance, extremely expensive fuel possessing before it’s us fuel in a nuclear reactor, and insurance that’s so expensive no private company is able to offer it.
Construction being the largest cost is really in reference to financing + construction + land + regulatory hurdles + any R&D costs. The direct construction costs run about twice what staffing does over the plant’s lifespan. However, because profits are so low and construction takes so long the loans must extend over decades which greatly inflates the cost of construction. On the flip side delaying decommissioning means the money set aside can grow before you’re forced to spend it.
As strange as it sounds lowering operating costs would actually reduce “construction” costs as you could pay back the loans sooner.
- ClumsyPilot 4y ago> Unfortunately this is not the case, decommissioning for example is extremely expensive though can be deferred for years. Well then closing plants makes even less sence, youll have to decomission them sooner
- Retric 4y agoI wouldn’t be sure of that. As I understand it, nuclear power plants are limited by corrosion so the end date for decommissioning is likely based on the power plants construction date not its final date of operation. There’s regulations that lost decommissioning must finish within 60 years of shutdown, but that stuff is often flexible in practice where physics isn’t.