The long term waste repository is a separate project, it is not included in the same project. The LCOE does include it however, as financing waste storage is ma
by Maakuth 4y ago
The long term waste repository is a separate project, it is not included in the same project. The LCOE does include it however, as financing waste storage is mandated in the law. I think what makes the LCOE so low is the fact that the plant vendor offered the construction as a turnkey solution with them covering the risk of overruns. So the price paid by the plant owner does not cover all the construction costs. In fact it's less than half of the costs.
edit: less than half