3 ms·
That's a figure with some bounce to it: Nuclear reactors connected to the grid in 2021 had a median construction time of 88 months. (7.3 years) [1] and
by defrost 4y ago
That's a figure with some bounce to it:
Nuclear reactors connected to the grid in 2021 had a median construction time of 88 months. (7.3 years) [1]
and
According to an International Atomic Energy Agency (IAEA) study, Tuesday, 15 countries have built a total of 83 nuclear plants over the last 20 years among the 31 countries with nuclear power. It took on average 190 months to build each plant.
During that period, Korea has built a total of 13 nuclear power plants. The average construction period for each plant was only 56 months (4.6 years), more than three times faster than other countries building nuclear plants. [2]
South Korea insists it meets Nuclear Safety and Security Commission standards, by contrast:
In France, [ ... ] taking an average of 126 months to build each plant, nearly three times as long as Japan. [2]
The United States has a total of 100 nuclear power plants, taking on average 272 months to complete one. [2]
[1] https://www.statista.com/statistics/712841/median-construction-time-for-reactors-since-1981/ https://www.statista.com/statistics/712841/median-constructi...
[2] https://www.scmp.com/news/asia/article/2027347/south-korea-second-fastest-nuclear-plant-building-country https://www.scmp.com/news/asia/article/2027347/south-korea-s...
- pyrale 4y ago> The United States has a total of 100 nuclear power plants, taking on average 272 months to complete one. Looks like one or two plants never finished.
- throwaway4aday 4y agoYou should definitely add the timelines for Japan and China from [2] Japan, which has built a total of eight nuclear power plants since 1996, was the fastest, taking only 46 months to build each plant, while China ranked third, building 28 nuclear power plants during that period and averaging 68 months to complete each one. Japan’s Kashiwazaki-Kariwa Nuclear Power Plant Unit 6 is the world’s fastest-built nuclear power plant, taking only 39 months for completion, while of Korea’s Wolseong Nuclear Power Plant Reactor 3 took 49 months to build.