> When there are unknowns, make a wide estimate. Convey the uncertainty. If the unknowns are ridiculous, make a ridiculous estimate. Even “5-200 days” is useful
by idopmstuff 4y ago
> When there are unknowns, make a wide estimate. Convey the uncertainty. If the unknowns are ridiculous, make a ridiculous estimate. Even “5-200 days” is useful because something else with less uncertainty can be chosen instead.
As a PM, I couldn't possibly agree more with this. When you give me 5-200 days instead of "we can't estimate this", you've started the beginning of a productive conversation. I can ask you questions about why the range is so big, and you can explain to me what steps we can take (research, narrowing scope, etc.), to reduce the range.
- jiggawatts 4y agoI’ve tried this. Inevitably the response is: “We need to book UAT testers for a specific date.” Ordinary LoB staff apparently are superstars that have their schedules locked in months into the future, but consultant SREs costing thousands a day can have their time wasted on a daily basis trying to determine how long it will take to complete a task that hasn’t even started yet. This has literally been my last two months. The dev team lead is asking me — an outsider — how long it’ll take his team to finish something. Not because I know better, but because he doesn’t know either and prefers to make it my fault because I’m expendable.
- roenxi 4y agoWell, analysing the situation that seems like quite an easy one to negotiate through: 1. Talk to the person who'll get angry at you when the UAT testers are brought in at the wrong time. 2. Make it clear to them, with a paper trail, that this is an impossible task and you can either book in a best-estimate with the likely outcome that the UAT testers will arrive and there will be nothing to test OR that you can book conservatively and there is a risk the project will be delayed waiting for UAT. They can pick which risk they want to bear. 3. Put in formal feedback, as loudly as possible, that booking in UAT for a specific time introduces obvious risks and someone needs to optimise the process to be more flexible otherwise it will delay projects & waste the businesses' money.
- 8note 4y agoAn interesting swap would be to get them to give an estimate for when they'd be ready for UAT, and then you take on booking the UAT. If you're the user or representing the user, shouldn't you be doing the UAT?
- re-thc 4y agoAren't we "agile" now? No UAT testers should be stuck for longer than a sprint's worth so just work it out closer to the date?
- alkonaut 4y agoDeadlines are a reality in all businesses (Real deadlines or made up ones). But if you have a thing to create that takes 5-200 days what will you do? You can pull a different estimate of 20-40 out of your behind when pressured to narrow it, and make the deadline 40 days. That might be a 50/50 hit/miss the deadline, with a worse case of running over to the full 200 day worse case (or even worse - even the 200 was a guesstimate). In some cases that's fine too. The decisionmaker might just want a date with 50% chance of hitting because it's better to land a sale and apologize for the delay, than to not land the sale and go bankrupt. The correct course of action though is to not set the deadline in that meeting. The 5-200 day estimate is a way of explaining "Either don't take this on at all, or at least don't try to schedule anything urgent based on it". In that case as a developer I'd suggest "Let me look at this for one afternoon, and I can return with an estimate that's 1/10th as large. Then let's meet again ad prioritize some work, schedule UAT and so on". PM's often look really surprised when they realize that all it takes might be to check if there is a functionality available already or if it needs to be implemented - which represented the difference between 5days and 200. If I go off and find it's already there, the estimate is 5-10, if I go off and find there is nothing and it has to be built from scratch, it's 150-200. But without that knowledge: 5-200. Or, if a 20-200 day estimate is actually due to real implementation uncertainty, I'd suggest "This is potentially large and uncertain. Let's try to break this apart if necessary into something that has a 10-20 day estimate and some parts that have a longer horizon. Schedule the delivery/UAT of the first functionality in 20 days, and we'll by then have a good estimate of when the remaining work will be done". If someone in my organization would try to convince me to pull a stupid estimate out of thin air, then pressure me to haircut that estimate, then schedule something based on it (such as a delivery), then pressure me to work overtime to meet it, then one of us would be leaving the org very soon.
- firstlink 4y ago> what steps we can take (research, narrowing scope, etc.), to reduce the range I quite literally quit my last job in February because of this shit[0]. Stop. No. These are not useful things for developers, much less senior developers, to spend their time on. 95% of my job ended up being coming up with estimates. My top deliverable to my management chain was estimates. They would only care about the actual development work insofar as it validated or invalidated the estimates deliverables. Hard facts: If time is such an unimportant resource that you're willing to waste most of it doing "research" and worrying about scope, then you don't actually need an estimate. For reporting purposes, just BS one yourself, that's literally your job as a PM. [0] It was well-paying, I was basically fucking around every week doing whatever I wanted, yet this issue alone outweighed all of that and was enough to make me quit.