Also if your write a clear specification with several tasks and don't change the specification. And you ask developers what it will take they will "Pad their es
by elviejo 15y ago
Also if your write a clear specification with several tasks and don't change the specification.
And you ask developers what it will take they will "Pad their estimates a little".
But the problem is that when they finish early they won't actually finish them they will test a little more, or polish it more etc.
Remember Parkinson's Law "Work expands so as to fill the time available for its completion." [1]
Now consider student's syndrome "Student syndrome refers to the phenomenon that many people will start to fully apply themselves to a task just at the last possible moment before a deadline." [2]
This two phenomena makes sure that in a project with multiple tasks time saved in a few of them won't be used in the tasks that take more than expected.
Based on this Ely Goldratt developed the Critical Chain Project Management methodology [3]
[1] http://en.wikipedia.org/wiki/Parkinsons_law http://en.wikipedia.org/wiki/Parkinsons_law
[2] http://en.wikipedia.org/wiki/Student_syndrome http://en.wikipedia.org/wiki/Student_syndrome
[3] http://en.wikipedia.org/wiki/Critical_Chain http://en.wikipedia.org/wiki/Critical_Chain