Oops: > EDF estimated the cost at €3.3 billion[6] and stated it would start commercial operations in 2012, after construction lasting 54 months.[7] The latest
by dividedbyzero 4y ago
Oops:
> EDF estimated the cost at €3.3 billion[6] and stated it would start commercial operations in 2012, after construction lasting 54 months.[7] The latest cost estimate (July 2020) is at €19.1 billion, with commissioning planned tentatively at the end of 2022.[8][2]
That's ten years late at 578% the projected cost.