That (3D-printing houses) is a non-solution or a solution to another problem. When building a house, the actual structure (walls/beams/decks) is very, very fas
by jaclaz 4y ago
That (3D-printing houses) is a non-solution or a solution to another problem.
When building a house, the actual structure (walls/beams/decks) is very, very fast to build, and if shorter times are needed, pre-fabrication is an already tested and working solution.
What takes time is before:
- site preparation
- excavations
- cableworls, pipes, etc.
- foundations
and after the naked structure is built:
- internal walls
- electric/hydrulic/etc. plants
- floors, pavement
- bathrooms and their fittings
- decoration/painting
- insulation/roof/waterproofing
- tests (if needed), etc.