No, it works for anything. The key that people misunderstand is that if the task is really uncertain, you're allowed to give a really wide range. In fact, you'r
by kqr 4y ago
No, it works for anything. The key that people misunderstand is that if the task is really uncertain, you're allowed to give a really wide range. In fact, you're supposed to -- that's the only way you can be correct 90 % of the time.
As a concrete example, I recently estimated "somewhere between 1 week and 4 months" when asked about an semi-well specified feature because I felt there's a 5 % chance it's done in less than a week, but even under pessimistic assumptions, there's about a 5 % risk it takes longer than 4 months.
When asked about a larger, unspecified projects a few years ago, I didn't hesitate to respond "between three months and 15 years". Sometimes that's the best you can do due to the uncertainties involved. It sounds useless, but it's really useful to have a quantitative measure of the uncertainty.