When I'm asked by my boss to estimate, I break it down for him. This part here I'm confident is 1-2 days of work, this part here can potentially be tricky so co
by magicalhippo 4y ago
When I'm asked by my boss to estimate, I break it down for him. This part here I'm confident is 1-2 days of work, this part here can potentially be tricky so could be 1 day could be a week, and this part here I can't tell without digging into the details.
If this is based on a customer request I'll try to find some restrictions he could take back to the customer to narrow the scope and provide a better estimate assuming those restrictions.
Most of the time this is all he needs.
- threatripper 4y agoWhat if he asks you for a number instead of a range? After all you have to use the company template to present your project and that does not have ranges on it.
- magicalhippo 4y agoIf for example, I say 3-7 days and he wants a single number because customer wants a date, he'll ask me "ok, so if I say to the customer they'll get the change in 10 days, we should be able to deliver?" Then I say yes, under the assumption of X, Y and Z that sounds realistic to me. Of course, sometimes the numbers are to high. That's where narrowing the scope or even finding a different solution comes in.