One thing to do is to show your estimates as distribution curves instead of averages. It can be helpful to choose estimates from a Fibonacci scale. Set the pess
by mch82 4y ago
One thing to do is to show your estimates as distribution curves instead of averages. It can be helpful to choose estimates from a Fibonacci scale. Set the pessimistic estimate high enough that it’ll rarely be missed.
Edit: I change the units based on how far out I’m estimating. If I’m estimating the next six weeks, I’ll use hours. If I’m estimating a roadmap I’ll use weeks. The numbers get large quickly (1 2 3 5 8 13 21 34 55 89 144). It’s rare you’ll find yourself planning farther than 2 years out (104 weeks).
As you work, keep updating the estimated time remaining. If the initial estimate for a task is an 8 (between 5 and 13), keep reporting 8 until your estimate falls below 8, then report 5 (between 3 and 8). Avoid reporting intermediate values like 7.