The parts of the job you can't estimate are actually your managers job to estimate. To illustrate that: > I am in the middle of developing X right now That on
by willcipriano 4y ago
The parts of the job you can't estimate are actually your managers job to estimate. To illustrate that:
> I am in the middle of developing X right now
That one you can estimate likely. It is a task that you can complete on your own without the rest of the organization. As a individual contributor you should be able to give a time frame for a task like this.
> I am also handling some bug requests related to unmentioned, previously delivered projects A and B
Software is going to have bugs, but I've never worked at a org that labeled bugs correctly. In my experience about half the time a so called bug is a specification miss or a feature request (a management problem), the other half need to be prioritized (again, management problem). If they want you to work on a bug over a project, deadlines are going to slip, and that is a management problem to solve. Your estimate of two weeks doesn't include washing the CEO's car or whatever other random task they want to pull you off to do, two weeks is two weeks and they gave you less than two weeks so of course it isn't done.
> I am in the planning stage for project Y, and working with client and analysts to pull some requirements together
So far you have been responsible for resource management to a large degree. You have to know in advance how many defects your software is going to have, how long it's going to take for a pull request to get reviewed, when the other team is going to get you what you need to complete the work, how often you will get pulled off to work on other tasks, etc. Now you are writing the requirements? What exactly is the management team doing if it isn't managing the product or the people building the product?
- smcl 4y agoWhat I was trying to say was that there are very valid reasons that mean I cannot and should not turn my attention to a distant project while I have my hands full right now. It doesn't mean I'll never do it, but it does mean that "I don't know right now, I need to complete some work before I can turn my attention to this properly" is not only a reasonable response but ultimately the correct one, rather than throwing out a number that I'll possibly be held to at a future date.
- willcipriano 4y ago"It's going to take me a couple days to put together a project plan, given that the project itself has yet to be fully defined. Shall I put project X on hold until I get that done?" Resourcing isn't a individual contributors problem, if it will take you a couple days to get a estimate, and they choose to prioritize that. Fine. If they don't want to give you the time, refuse to speculate, if they keep pushing, tell them it will take a year or some other large number that you could do it 2 - 3 times over in. If they say it won't take that long, ask them how they know since the project isn't defined.
- smcl 4y agoAh yeah those are some good strategies and they're usually how I approach this when it comes up so I think we are on the same page :) It's just tiresome to have to do, and I feel like in doing so despite being polite and calm I think I'm being thought of as obstinate or a troublemaker. Which is a shame because in fact I'm trying to reduce the uncertainty and chaos and make everyone's lives a bit nicer :) Oh well, like I said it doesn't come up often enough to cause me great stress and I'm experienced enough to sort of handle myself when it does. Just ... I wish it didn't :D