Damn, that is expensive. 100 ppl x 8hrs x 4d x $150/hr = $480000. A half-million dollars to plan the next 3 months… and that’s assuming those were relatively l
by moistly 4y ago
Damn, that is expensive. 100 ppl x 8hrs x 4d x $150/hr = $480000. A half-million dollars to plan the next 3 months… and that’s assuming those were relatively low-paid people ($100/hr x 50% overhead costs).
- vesinisa 4y agoIt really speaks volumes to how gullible the high level managers who buy into SAFe are - and how good the SAFe consultants are at selling their "method". These people have probably ran the numbers and still somehow believe the investment is worth it in increased efficiency. Little do they know all the useless planning is probably just hurting them more than helping - the investment has negative value even before subtracting the cost of tied up employee resources. Madness!