This is a common conflict! One perspective says that idle engineers cost money, so you should load up your engineers to 99 % utilisation with a huge backlog of
by kqr 5y ago
This is a common conflict!
One perspective says that idle engineers cost money, so you should load up your engineers to 99 % utilisation with a huge backlog of tasks. The consequence of this is that tasks take, on average, months to complete because they sit idle most of the time, not being worked on.
The other perspective is that idle tasks is what's expensive. Thus you must keep your engineers lightly loaded (say 70 %) so they can, in your words, pounce on new tasks. With this setup, most tasks spend a negligible time waiting and most time actively worked on.
Now, how can idle tasks be more expensive than idle engineers? There are whole books dedicated to explaining this. I'd recommend starting with Reinertsen's Principles of Product Development Flow.
- thraxil 4y agoIt's always kind of amazing that so many engineers (and engineers turned manager) have encountered enough queuing theory to understand that if they keep a CPU at 99% utilization, it will have a detrimental effect on task latency, but can't understand how to apply that same reasoning to engineer utilization.
- Brian_K_White 4y agoAn engineer knows where analogies apply and where they don't. My pool of available work is not impacting whatever I happen to be working on at the moment. I am not doing 1 second of work on 60 different projects every minute.