12 years full-time, self employed in consulting, contracting, freelancing has taught me this. Customers just don't want surprises of poor estimates. If you ca
by j45 15y ago
12 years full-time, self employed in consulting, contracting, freelancing has taught me this.
Customers just don't want surprises of poor estimates. If you can build trust and a track record of that even the most neurotic customer will find some peace and solace in you.
The goal for you and the easiest way is to learn:
1) When you quote, say "Up to X hours".
2) Provide updates
3) Don't go over
While you get accurate enough to do that...
Learn to understand it's about trust, and value. If you generate more value than what you're paid (2x to 10x more), the client will never, ever care. If the good things you say, happen, you will have a track record and leeway.
Learn to work Value based instead of hourly. To get good at it take your estimate, and add 30-40% to it as a guess (on the side) to see how accurate you are.
My formula is this to estimate any project:
TOTAL HRS = (estimated hours) * (number of unknowns) * (complexity of unknowns) * (the percentage I'm usually off in my estimates) * (pain-in-the-ass tax)
(ESTIMATED HOURS) - This is your best, educated, guess of what you KNOW and have EXPERIENCE in ESTIMATING regularly.
(number of unknowns) - I use this as a multiplier in tenths. Ie., 2 unknowns makes this = 1.2
(size of unknowns) - For each unknown sometimes its a small thing with a deep possible impact, or a lot of unknowns all over the place with small impacts. Either way, I have to put a multiplier to it in tenths. So, if each of my 2 unknowns was a small but deep item, I'd give it a .3 and the other item was small and something I can stumble my way through, I might give it a .1 for a total multiplier of 1.4
(accuracy adjustment) - Some people are always 5-30% off consistently in their estimates, for each person, put in their estimate
(pain-in-the-ass -PITA tax) - Rarely used, but for high maintenance clients who take up more time than they should. The more updates, talking, arguing and convincing you have to do, it's billable time because you're working for them, about their project. Factor it in as a multiplier.
My formula in this case could look like this
Total hours = 20h estimated * 1.2 (unknowns) * 1.4 (unknown impacts) * 1.1 (accuracy adjustment) * 1.2 (PITA)
Total hours = ~ 44 hours
And that's how a project ends up taking twice as long as you thought :)
Tools to use: I use a mix of Freshbooks and a case manager like Fogbugz. Freshbooks ought to keep you sorted how you need.