Again, not that simple. The customer restore procedure was almost certainly tested(and in active use as customers blow up their own data often enough). It was
by largbae 4y ago
Again, not that simple. The customer restore procedure was almost certainly tested(and in active use as customers blow up their own data often enough). It was _not_ tested on 800 customer stacks simultaneously, as that was considered a sitewide disaster by whoever dreamed up the failure modes to test for. Meanwhile the actual whole site disaster restore plan may or may not have been tested, but it was useless for this case since some customers were unaffected and would be damaged by the whole site plan.
- baskethead 4y agoThen we are in agreement. Even if it were the case they had to do 800 separate recoveries (which I vaguely remember reading they couldn't do it individually), it means they never tested a large scale recovery situation and had no idea that 800 recoveries would take 2 weeks. That's a significant issue that they should have tested.