If the project is planned according to median, you accept up front that there is 50% chance the project will be late.
by mirekrusin 5y ago
If the project is planned according to median, you accept up front that there is 50% chance the project will be late.
- waqf 5y agoIt's worse than that. You need the median time for the whole project, which you can't get just from summing the medians of the individual tasks.