3 ms·
Very hard. Lots of stuff out of certification unless they were mothballed with the explicit goal of being restartable, if the fuel has been removed it will be w
by jacquesm 5y ago
Very hard. Lots of stuff out of certification unless they were mothballed with the explicit goal of being restartable, if the fuel has been removed it will be weeks at a minimum, but more likely months assuming that it is possible at all.
- throwthere 5y agoInteresting. So at a pretty large expense do you think it’s something that could be done before next winter?
- jacquesm 5y agoTough question, there are a number of nuclear plant engineers on HN that should be able to give more clarity. When Pickering shut down in Ontario because of the powerfailure the shutdown took less than a minute, the restart took more than two weeks. And that was with a fully fueled operationally ready plant. Refueling is a month or so normally, but what I am wondering about is if you leave a plant like that powered off for a while without the express goal of restarting it (besides the removal of the fuel) how much of it will require refurbishing before it can all work again. I would expect that the whole plant would need to be recertified before it could be operated again.
- jacquesm 5y agoSo, some more reading later: there is a 'post operational' phase prior to the actual decomissioning when stuff starts to be taken apart and removed. I think the question to be answered is whether or not these plants are still in the 'post operational' phase or whether there has already been decommissioning, so far I have not been able to find anything definitive on this.