> When the United States built nuclear plants at scale, in serial production, plant costs were also much lower. As far as I know, there was never a time where
by magicalist 5y ago
> When the United States built nuclear plants at scale, in serial production, plant costs were also much lower.
As far as I know, there was never a time where US nuclear power plants were built on time and at budget (and that's while building more than France ever did).
- Manuel_D 5y agoDuring the 1970s, plants were built at 1-2 billion per GW of capacity: https://ars.els-cdn.com/content/image/1-s2.0-S0301421516300106-gr2.jpg https://ars.els-cdn.com/content/image/1-s2.0-S03014215163001...
- magicalist 5y agoThey were still over budget and late, but that chart (which was created to try to claim all the overhead can largely be explained by regulatory changes) strongly argues against > When the United States built nuclear plants at scale, in serial production, plant costs were also much lower.
- Manuel_D 5y agoSee this cluster of power plants in the second half of the 1960 [1]? This is when lots of plants were built around the same time, leveraging economies of scale. All of those plants were built at less than $2 billion per gigawatt of capacity, most of them closer to $1B per GW. This is about an order of magnitude less than the one-off construction that's been done since then. 1. https://i.imgur.com/yKqGXyL.png https://i.imgur.com/yKqGXyL.png
- magicalist 5y agoThose are construction start dates, and construction duration in that era took 5-10 years in that era according to that paper. Construction of that cluster overlapped considerably with the later more expensive plants (some even finishing after 1979).
- Manuel_D 5y agoI'm still unsure how you think this contradicts the claim that plants built together, in series, were cheaper than building smaller numbers of plants. Yes, those plants took 5-10 years to build. And? This doesn't change the fact that they were built for ~$1.5B per GW of capacity. The last of these plants were finished as construction started on later plants that would come online during the 1980s or 90s, and those later plants were much more expensive. But there were also fewer of them which leads to less economy of scale. Let's put this in simpler terms: * Lots of plants that started construction in the 1960s-1970s time frame -> lower cost per GW * Smaller number of plants started in the 1970s and beyond -> higher cost per GW Thus, a strong relationship between a greater number of plants build built and lower cost per plant. Construction time frame doesn't matter much. If 100 plants are started in 1965 and finished in 1980 and 10 plants are started in 1975 and finished in 1990, the 5 years of overlap doesn't change the fact that the former is going to have a much better economy of scale than the latter.