Prioritization, multiple work streams, unplanned work
- usr1106 5y agoMakes a lot of sense to me. In a smaller start-up that already serves real customers team size is more like 2-4 and there are at least 3 streams per engineer. No, it doesn't work well. Who has seen something completely different in real life?
- mason55 5y agoI’ve certainly seen it different because I make sure it happens. What you’re talking about is the human equivalent of tech debt. Occasionally you need to take out a loan, but you had better have a good reason why and a plan to pay it back. If there’s crunch to get something live and then people scale back, that’s one thing. But if the product/company/whatever is only successful if people work in an unsustainable way then it’s not actually successful. Better to understand that before everyone is burned out and miserable.
- someguydave 5y agoSalesmen tend to sell regardless if you can execute or not.
- jcims 5y agoI just switched to managing a scrum team that is absolutely completely under water. We spend half of our time fighting fires and the other half trying to solve everyone’s problems. I got so distracted cutting old ties, applying tourniquets and trying to learn the ins and outs of the system that I didn’t realize I was burning out the product team by not helping enough (at all really) with planning. Lessons learned. Beers to buy.
- Buttons840 5y ago> Optimize for finishing work before starting new work Part of this is, as a developer, I really want to be able to have a few days of relatively relaxed work at the end of a project. Maybe just check some logs, make sure things are running okay, pay off some technical debt, talk with coworkers about work or not work. This almost never seems to happen, while delivering one thing the team frantically looks to the next. People need periods of work and rest.
- losteric 5y agoIf you're on a sprint process, I've found it quite helpful for whoever is involved in estimation to target a "P90-confidence" estimate and round up the points... fighting the tendency towards "average" estimation (which invariably leads to crunch). For changes that ship below estimation, use the time to vet the feature or work on other - don't immediately pick up the next sprint task. In essence, estimate and operate with sustainability in mind.
- 9wzYQbTYsAIc 5y agoI like that idea; based on my experience, targeting with confidence intervals sounds way better than a plain average. I used to do something similar to that by making high and low estimates for each effort unit and then using the average of averages. That approach might work well for teams without a basis in operations research or statistics.
- kqr 5y agoThe strong benefit of confidence intervals is that they are empirically verifiable. If you go back and look at your past 90 % estimates and you find that not roughly 9 out of 10 were correct, you need to revise your process. Averages of averages lack this very practical, immediate interpretation.
- Buttons840 5y agoThe sum of normal distributions is a normal distribution.
- mirekrusin 5y agoYes, people don't realize that median estimate means they're expecting up front 50% chance it won't be on time, in their heads it's something weird like "almost 100% will be finished on time".
- moltar 5y agoYea!! This! I’ve been working with a therapist for a few years. And that’s one of the things we’ve discussed that’s important for mental health. We need to digest, reminisce, retrospect, whatever you want to call it to get closure. If you don’t get closure then you have open loops that are mentally taxing.
- Teafling 5y agoI started scrum mastering a team in November and the team suffers from too many things at the same time for sure. I have to take a more proactive planning role and I could definitely try out that on call stream idea. I am naturally a quite chaotic person, I have trouble helping other people create order when I'm already having trouble keeping an eye on all the streams that exist in the team. Any tips would be appreciated. I wish people would stop bringing up the Pareto principle. "Some things are consistently bigger than other things." Can we talk about why things are bigger than other things instead of saying it's because of some law of nature?
- crowdswisdom 5y ago> I wish people would stop bringing up the Pareto principle. "Some things are consistently bigger than other things." Can we talk about why things are bigger than other things instead of saying it's because of some law of nature? I see what you're saying, but it sounds like you haven't really internalized the principle.. because you're viewing it as a tautology rather than the useful heuristic it is. You can and should still have the probing discussions. But having 80/20 as a rule of thumb will actually help you know where to probe. So you might want to give it another look. > I am naturally a quite chaotic person, I have trouble helping other people create order when I'm already having trouble keeping an eye on all the streams that exist in the team. Any tips would be appreciated. There's so much to say about this topic.. it's hard to give many pointed tips. But my advice would be to 1) read far and wide about product management (blog posts like this one, books, research, etc), and especially focus on first principles. 2) Experiment with your team! and 3) *Do not* think that doing one of those weekend certification courses or seminars or whatever is going to help much. Points 1 and 2 will give you far far more insight.
- Teafling 5y agoThanks for your thoughtful reply! Re: pareto principle, I've never actually looked at what the principle means. "80% of the consequences come from 20% of the causes" is quite useful, as I understand it it means "don't assume that causes of consequences are randomly distributed". I think I see it often misunderstood the way I misunderstood (/misunderstand?) it: "As with most things, there is the 80/20 rule (Pareto again), exceptions are sometimes warranted in important situations." this sentence just says "you should stick to the rule about 80% of the time" Re: advice, thanks for taking the time! I hadn't considered research, but luckily I already agree with 3) :P
- sudofail 5y agoWe do something very similar to what's laid out here. One note on the On-Call stream though. We've found that On-Call can become a catch-all, and force engineers to work in domains they have no familiarity with. It hasn't worked very well for us.
- dilyevsky 5y agoWhy do you have people carrying pagers for systems they have no familiarity with is the question I would ask.
- Too 5y agoOn-call stream in the context of TFA doesn’t imply carry a pager. It’s a first line of defense role to protect rest of the team from any kinds of interruptions during daily feature development. We’ve also tried it and as parent describes it can be a bit problematic as you often have domain specific experts within the team, who are the best to solve particular issues, especially as fires often should be put out quickly. What you need to do in such case is to check if you can accept a slightly longer fire, refrain yourself from interrupting the expert and see the situation as a learning experience. Often debugging something is the best way to learn.
- kitsune_ 5y agoI think most of the work stream principles outlined in the article are sound, however, in my view having a manager dictate finely detailed priorities is in most situations an anti-pattern and a Taylorist trap. In my experience, heuristics that help people identify priorities themselves are usually more powerful. You can still break ties or give relative prioritizations when needed.
- someguydave 5y agoIt's much better when managers prioritize than when they do not and let everything be urgent.
- 8note 5y agoI think what you're really saying is that it's nice when managers deprioritize items
- someguydave 5y agomostly yes. I think humans can only work on one thing at a time. If you hire a worker it is common sense that you should be able to identify that upon which he should work.
- kqr 5y agoBut this is the Taylorist trap mentioned in the top level comment. That somehow "managers" are hired to think, and "workers" are hired to do whatever the "managers" say. I fully expect the "workers" I supervise to be able to identify things which need work completely on their own. Many heads think much better than one. Besides, they are on the frontlines so they have a much better view of the situation than I. (As much as I try to also do technical work myself.)
- someguydave 5y agoI understand. To me you resolve the paradox by getting management to admit to themselves that most engineers and programmers are also managers and need some explicit authorities to decide what needs to be done or not
- 8note 5y agoMy team goes back and forth between having each member doing individual stories, then getting together to quickly close big projects by scheduling all the stories in parallel. Everyone enjoys the big parallel work, but it's really hard to set up projects to do that, and also deprioritize other items so we can focus. We have a giant surface area though, so one stream per person is as few streams as we can manage most of the time
- quadrifoliate 5y agoThe "Expect the unexpected" part of this is, frankly speaking, bullshit. It has sentences that are a contradiction in terms, like "Planning should reflect an unplanned work allocation". The problem is that if you put aside, say 20% of time for unplanned work, this is effectively broadcasting to all the teams around you "Oh, we have planned 20% downtime", and they will feel extra vindicated in asking you to do stuff for them as part of this "unplanned work". This is in addition to the bevy of middle manager vanity meetings, all-hands, quarterly meetings, and a bevy of other useless meetings that managers seem to be able to put on their developers' calendars seemingly on a whim. The only correct advice, and one that is not put into this because it is unpalatable to someone posting "thoughts on leadership" is to push back hard on "unplanned work" in addition to leaving some slack time in planning. Otherwise you will end up with the typical developer who feels constantly threatened by management and has one foot out the door.
- kqr 5y agoAnother option I like is shortening the planning horizon. That way, you actually get to plan a lot of what otherwise count as unplanned work. If you try to plan the next three months ahead of time, you'll either be doing a lot of unplanned work or doggedly sticking to a plan that's out of date and ineffective. If you try to plan for the next two weeks, you actually have a small chance of accounting for what's going to happen in this period. In some industries, you have to make that two days. I think Reinertsen uses the example of searching for a submarine. The area it can be in after one sighting grows with the square of time (it's a circle whose radius is determined by speed.) If you haven't found it within a few hours of sighting, you might as well give up because by that time the search area expands faster than you can conduct a search. Planning is similar.
- codeflo 5y agoI have a similar take on stuff pushed onto the dev team. I think it’s often not the unplannedness of this work that’s at the root of the problem but its low value. Pushing back against actually important unplanned work would be harmful — and usually nobody does that, which shows that it’s not actually about planning. The point is, at least in my experience, many orgs have lots of other teams running around with ideas for things the dev team might do for them. Many of those are just not very important in the grand scheme of things. A lot less important, for example, than keeping the codebase healthy. But it’s usually not politically convenient to say that explicitly. It’s much easier to “shut them up” by citing schedule pressure. Of course, this tactic backfires hard whenever there’s even a hint of downtime.