PM guru Eliyahu Goldratt advocated for a 50% likelihood of completion with no buffers for individual tasks, but one shared global project buffer. I don’t think
by aranchelk 5y ago
PM guru Eliyahu Goldratt advocated for a 50% likelihood of completion with no buffers for individual tasks, but one shared global project buffer.
I don’t think there’s a single right answer for that percentage, but the key is that it should be determined by the person or group defining the global buffer and should be done with consideration for the distribution of possible durations the project tasks might take.
- willcipriano 5y agoWouldn't that mean in a ideal world half the estimates will be under? That buffer would have to be half the size of the total project or so.
- aranchelk 5y agoThe expectation when removing per task buffers is that some estimation errors for individual tasks will be high and others low so ultimately to an extent they'll cancel each other out. In Goldratt's system, the risk comes from the longest (in terms of duration) chain of dependent tasks. Delays early in the chain can only be canceled out by speed ups in later dependent tasks, that's the primary motivation for that global buffer. The technique was adapted from factory production line optimization. The case can be made that it can work well for projects doing repeatable and thoroughly understood things like constructing buildings. There are reasons it's not a slam dunk for software, but IMO there's still a lot to learn from his work.