That site may overestimate the cost of dealing with intermittency, since it doesn't include dispatchable demand. For example, if hydrogen is to be used in stee
by pfdietz 5y ago
That site may overestimate the cost of dealing with intermittency, since it doesn't include dispatchable demand. For example, if hydrogen is to be used in steelmaking or ammonia synthesis, that demand can also be added when renewables would otherwise be curtailed, and the hydrogen stored for later use.
The site's model also does not include pumped hydro, or intermediate term thermal storage.
All these extra options can only help reduce the cost of integrating renewables, and make renewables more competitive vs. nuclear.
- ephbit 5y ago> ... dispatchable demand. For example, if hydrogen is to be used in steelmaking or ammonia synthesis, that demand can also be added when renewables would otherwise be curtailed, and the hydrogen stored for later use. Isn't the problem that electrolyzers mostly have to run 24/7 because they would otherwise not be profitable? Then all these processes that rely on hydrogen wouldn't actually belong to the dispatchable demand category. Dispatchable demand could be found in heat pumps (in combination with buffer tanks) for heating homes. (As long as there's sufficient grid capacity)
- pfdietz 5y agoWhen the idea was to turn relatively expensive electricity into hydrogen to replace gasoline, then it made sense to make the electrolyzers as efficient as practical, even if that made them more expensive. But using curtailed intermittent power is different: here, the electricity is cheap, and capital cost of the electrolyzer becomes more important than efficiency. Under these different design tradeoffs, one might use a different technology (alkaline electrolyzers without platinium group catalysts, say, rather than PEM cells with expensive Nafion membranes and platinum.) I have seen claims that alkaline electrolyzers are available for < $200/kW in China.
- p_l 5y agoPumped hydro has the problem of "we pretty much can't build more". As for curtailment-reducing tricks, that's a good argument but IMO not changing the base calculus much - the model is about replacing the base demand power sources, so that we can push the extra into peak. Bigger problem is that scaling down demand is problematic for dealing with underproduction, and also simply missing on power (Thus my preference for billing for dispatchable power generation, then extra peak could be funneled easier into bonus things like green hydrogen for non-storage etc.)
- pfdietz 5y ago> Pumped hydro has the problem of "we pretty much can't build more". On-river pumped hydro is not easily expanded. But there is enormous potential for off-river pumped hydro. http://re100.eng.anu.edu.au/global/ http://re100.eng.anu.edu.au/global/
- p_l 5y agoConsider the large missing areas on the map. For example, Poland and Germany has 0 sites (Poland pretty much built all hydro it could without causing more environment damage)
- pfdietz 5y agoThat's certainly true, but it's also certainly true that "we can't build anymore" is by no means universally true. Great swathes of the world have far more PHES potential than they need.