Waterfall can be fast. In fact, done properly, it is the fastest technique of them all.
by boffinAudio 5y ago
Waterfall can be fast. In fact, done properly, it is the fastest technique of them all.
- rubidium 5y agoThis. If you properly understand the problem. If your team is compact enough to be in the same room. And your customer input during concept/requirement writing is high. If you stray outside that, both waterfall and agile struggle… but waterfall has the potential fatal flaw of delivering a product no one wants (or doesn’t work). This is why agile was introduced. There were software products being made that ended up just not working… so people saw that problem and tried to fix it with agile. But agile just fixes the “don’t deliver a product that doesn’t work” problem.
- regularfry 5y agoIt's more subtle than that. What "agile" does (both Scrum and XP, historically) is _protect the delivery team_. With waterfall-style project management, early errors balloon but often don't surface as something that needs addressing until implementation and testing, so the delivery team gets all the stress for blowing out the project schedule. Agile techniques both surface those errors early, so they're course-corrected quickly, and provide a set of clear rules for the rest of the organisation to abide by which should mean that the delivery team can't get overloaded into a deathmarch.
- lbriner 5y ago> done properly And herein lies the rub. If a project is more than 6 months to a year in duration, there is very little chance that what the customer now wants is what they wanted before. Requirements aren't created instantly on day 1 ready for dev, you could easily have several years of requirements, during which time people change, the world changes, the law changes, priority changes and then what? Even systems that are relatively unchanging like the air traffic control system they built in the UK still had a whole raft of issues that needed addressing and at this point, the documentation becomes out-of-date and changes are extortionately more expensive to resolve.
- fer 5y ago> If a project is more than 6 months to a year in duration, there is very little chance that what the customer now wants is what they wanted before. Depends largely on the customer. Just do anything defence, related to aircraft, or industrial control systems, more often than not, requirements are set in stone, and modifications require approval and consequent fees. Now, those industries throw a lot of money at actual R&D to know what requirements can be requested, which is very different from your usual software shop, where "R&D" is some brief talk during refinement or at most a dedicated user story to look into the subject.
- Kim_Bruning 5y agoFor "small" projects having requirements set in stone (probably?) works fine. The customer might claim something different, but for a couple of large and failing projects in industrial automation I've had to fight hard to be able to iterate and rescue them from the jaws of defeat. You've had different experience?
- aahortwwy 5y ago> done properly "You're doing it wrong" is not a compelling argument. A competent, motivated, invested, and empowered team don't need any particular methodology to succeed. Methodologies are adopted precisely because many people don't do things properly much of the time. A methodology which doesn't account for this and doesn't self-correct when done improperly isn't worth a whole lot. Waterfall done properly produces great results. Agile done properly produces great results. Both of them produce bad results when done poorly. Proponents of one tend to compare their methodology done properly to alternative methodologies done poorly. That's a pointless conversation to have.