Among other things, Extreme Programming says that estimates increasingly diverge from reality if they're longer than three weeks. So: Do you need accurate est
by AnimalMuppet 5y ago
Among other things, Extreme Programming says that estimates increasingly diverge from reality if they're longer than three weeks. So: Do you need accurate estimates? Then you need detail. The fuzzier the estimates can be, the less detail you need.
Do you need developers to do the detailed estimates? Yes, for two reasons. Politically/socially/culturally, having someone else telling you how long something is going to take you to do is... not received well, given normal human nature. Functionally, the developers have to be the ones to do the detailed estimates, because they're the ones who actually know what the details are.
All that said... overly detailed estimates are a waste of time. Don't break it down into a series of tasks, each of which take one hour or one day.