I think the methods are well known, they just take time. Rough estimates do have their value (is this a 1 day feature, 1 month feature, 1 year feature?), proble
by tsimionescu 5y ago
I think the methods are well known, they just take time. Rough estimates do have their value (is this a 1 day feature, 1 month feature, 1 year feature?), problem is when someone starts adding rough estimates to project a date.
To get a real date, you run a feasibility study - you do PoCs, you deep dive on features etc. Then, you freeze the requirements and implement based on the study.
This will probably take around a quarter of the total time of the project.
Alternatively, you stick to rough estimates, and you will get roughly the features you asked for in roughly the timeframe estimated.
- Lutger 5y agoYou could do both. Begin with a rough estimate, preferably a range (order of magnitude). If this gets greenlit, do all the things you mentioned but also just start on the project. Iterate on the estimate like you iterate on the deliverables, the estimation will get increasingly accurate as you develop. There's a bit more upfront work here that goes into the estimation, but it won't be like 25% of it is pure waste. Maybe 5 to 10%, depends on what the quality of the estimate must be. Somehow this never works in practice though, I suspect the initial guesstimate will prime the expectations of everyone involved and will be seen as a target. Clients will be disappointed if the project takes longer and frame it as such (it's late, takes longer, over budget, etc.). I suspect that in order for this to work, the initial range must be large and the adjusted estimates in the project as well as the delivery date must fall within this range. I think this is a basic function of trust: will these people do as they say or not?