Fair but this is the thing we all do wrong with estimates. I've come to the following system that I think works well and captures the uncertainty. Estimates ar
by snarf21 5y ago
Fair but this is the thing we all do wrong with estimates. I've come to the following system that I think works well and captures the uncertainty.
Estimates are given as the following choices: hours, days, weeks, months, quarters. You never give a number tp the units. These all mean some "small number of X" where X is the list above. Then if Product has a question like, "Why would Z take weeks?" then you can have a discussion about the complexities and the task can be further refined and/or split into multiple things and those can be estimated as above, rinse and repeat.