> the 2 units at Civaux Nuclear Power Plant, took 13 and 11 years from construction start in 1988/1991 to commercial operation in 2002: At the time France was
by natmaka 5y ago
> the 2 units at Civaux Nuclear Power Plant, took 13 and 11 years from construction start in 1988/1991 to commercial operation in 2002:
At the time France was simultaneously building many reactors, see:
https://fr.wikipedia.org/wiki/Liste_des_r%C3%A9acteurs_nucl%C3%A9aires_en_France#/media/Fichier:Chrono-parc-nucleaire-francais.svg https://fr.wikipedia.org/wiki/Liste_des_r%C3%A9acteurs_nucl%...
Some say that Flamanville-3 is a failure because it should be built along with many other reactors. This seems ridiculous to me, as if the problems (lack of adequate applied skill, bad project management... there is a complete official report about the causes, written by M. Folz) would be alleviated by parallelizing projects (it would instead worsen their effects and add delays).
> if they published optimistic numbers because they thought that there was more institutional tolerance
In France institutional tolerance for the nuclear industry is at its max. Start in 2007, to be delivered in 2012, nothing delivered in 2021 and 5.6 times over-budget... and no-one even talks about calling it off. Even better: M. Macron wants to start new projects!
- toyg 5y ago> In France institutional tolerance for the nuclear industry is at its max. At this point, it's more of a jobs-program than an energy-program - like a lot of US defence spending.