> That just reflects the size and complexity of stories they're asked to estimate. In any reasonably complex application even the smallest task will likely not
by wingerlang 5y ago
> That just reflects the size and complexity of stories they're asked to estimate.
In any reasonably complex application even the smallest task will likely not be available to anyone in under a week anyway. Need to change a button? Sure, that's an hour or two to change it and ensure it didn't break some other scenario. Maybe that takes another day or so to verify with team X or dev Y in a PR. Wait for tests and processing for release to QA environment. Maybe another roundtrip if something is found, at which point you might be working on another button. Then it sits for a while until it can catch a production push.
I'm also assuming that the senior dev is working in a fairly large machine. If it's a startup then sure, anything goes depending on what shortcuts are in place.