On the contrary, our major nuclear R&D company messed up an extension of the Flamanville nuclear plant multiple times: https://en.wikipedia.org/wiki/Flamanville
by joconde 5y ago
On the contrary, our major nuclear R&D company messed up an extension of the Flamanville nuclear plant multiple times: https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plant https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plan...
- meshenna 5y agoAlso see Olkiluoto 3 in Finland: https://en.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plant#Unit_3 https://en.wikipedia.org/wiki/Olkiluoto_Nuclear_Power_Plant#... "The main contractor, Areva, is building the unit for a fixed price of €3 billion, so in principle, any construction costs above that price fall on Areva. In July 2012, those overruns were estimated at more than €2 billion, and in December 2012, Areva estimated that the full cost of building the reactor would be about €8.5 billion, well over the previous estimate of €6.4 billion."