For predicting the daily schedules on a film set I always "ran a simulation" of what would be done that day and just summed the predicted minutes. The simulatio
by atoav 5y ago
For predicting the daily schedules on a film set I always "ran a simulation" of what would be done that day and just summed the predicted minutes. The simulation ran in my head of course, but it included things like: Actors drinking coffee and chatting, costumes getting ready, Camera department forgot memory card in the car, lunch breaks, someone arrives late, etc.
Obviously the major chunk were always scenes and they are usually also the major contributor to the insecurity of the prediction. E.g. working with people who you don't know, weather, technical problems (broken, missing stuff), stuff that just won't work (animals, certain scenes with actors).
But in the end what always mattered was that there was a time plan for each day and at the end of a day we would know wheter we are A) faster as predicted, B) on time or C) slower than predicted. The next day would then be restructured accordingly by the production and usually you'd be back on time by the end of that.
I was usually spot on with my predictions and we never had any issue with getting the planned stuff done.
With programming the whole thing is harder, because it can be even more unpredictable. But what definitly always helps is when you have a feeling for whether you are too slow, on time or you managed to build a time buffer for future doom.
- regularfry 5y agoTom DeMarco talks about modelling-based estimates in Waltzing With Bears, mainly to break people out of the error they fall into of treating the soonest possible time something could be done as a realistic estimate of when something will actually be finished. There are also approaches like Function Point Analysis which provide an explicit model that you can calibrate your team against. It's doable, but what people tend to forget is that it's work. If you want an estimate, I need to be able to expend effort providing it. It's an engineering activity that needs organisational support to do it at all well, but often you find an expectation that people will be able to pull an estimate out of a hat just having heard the faintest description of the problem, and there can often be a tacit belief (usually but not entirely from non-technical folks) that not being able to do so makes one incompetent.
- kqr 5y agoThis is where range-based estimations really shine. If you want an estimation right now, I will tell you on the spot that, "I'm 95 % certain it will be done no later than nine months from now, but probably sooner. However, I know it won't be done this week." You want a narrower range than 0.25–9 months? You'll have to let me think about it. Maybe I can be just as certain that it will be done 1–5 months from now, if I get time to mentally run through the simulation, to borrow the terminology from upthread. You want a narrower range than 1–5 months? I don't have the information I need to give you that. If you give me a couple of weeks to talk to the right people and start designing/implementing it, the next time we talk, maybe I have gotten the range down to 1–3 months. I can always give you an honest range, but the more you let me work on it, the narrower it gets. ---- This is of course what's suggested in How To Measure Anything, Rapid Development, and any other text that treats estimation sensibly. An estimation has two components: location and uncertainty. You won't ever get around that, and by quoting a single number you're just setting yourself up for failure.
- jaymzcampbell 5y agoI've been finding this approach incredibly useful too with teams and trying to manage the needs and concerns of business vs product vs engineering. I quite liked how it's described here: https://spin.atomicobject.com/2009/01/14/making-better-estimates-range-estimates/ https://spin.atomicobject.com/2009/01/14/making-better-estim...
- kqr 5y agoWhat I disagree with when it comes to fuzzy labels like "aggressive but possible" or "highly probable" is that they're still unverifiable and, frankly, just as meaningless as point estimates. This is where actual probabilities come in: if you give me 90 % probability ranges (i.e. you think there's a 90 % chance the actual time taken will fall inside the range you give me) that provides me with three extremely powerful tools: 1. First of all, I can use Monte Carlo techniques to combine multiple such estimations in a way that makes sense. This can be useful e.g. to reduce uncertainty of an ensemble of estimations. You can't do that with fuzzy labels because one person's range will be a 50 % estimation and someone else's will be an 80 % one. 2. I can now work these ranges into economic calculations. The expected value of something is the probability times consequence. But it takes a probability. 3. Third, but perhaps even more important: I can now verify whether you're full of shit or not (okay, the nicer technical term is "whether you're well-calibrated or not".) If you keep giving me 90 % ranges, then you can be sure I'm going to collect these and make sure that historically, the actual time taken falls into that range nine out of ten times. If it's not, you are overconfident and can be trained to be less confident. The last point is the real game changer. A point estimate, or an estimate based on fuzzy labels, cannot ever be verified. Proper 90 % ranges (or whatever probability range you prefer) can be verified. Suddenly, you can start applying the scientific method to estimation. That's where you'll really take off.
- frazbin 5y agodang, software planning is harder than herding hundreds of entertainment people? Not what I would have expected! I always assumed the 'unknown unknowns' were much larger in real life enterprises than in software ones, and that'd make planning harder. A lot of advantages come from software being made out of formal systems.
- kqr 5y agoSoftware has variability spanning multiple orders of magnitude. In entertainment, you might get one or two extras fewer or more than you needed, but you won't suddenly stand there with a hundred or thousand times more extras than you needed. Similarly, equipment will be hours or days away from where it's supposed to be, but you won't suddenly find out it got dumped on another planet. Why does software have such extreme orders-of-magnitude variability? Anyone's guess. I like the perspective that software is made out of many pieces of little software, which are in turn made of even more smaller pieces of software. That fractal nature is a qualitative difference to people, which are not made of many tiny people. (As far as I know.)
- atoav 5y agoShooting a film is very much an act of discipline to a nearly militaristic degree if you are on a good set and the film isn't trying crazy new experimental things. You can know really well how long a light person will take to do a thing, or how long the camera will take to find an angle. Knowing when your client will move their arse to send you the test_data.csv is very much unknowable.