Well, currently the French are buildin a new nuclear power plant in Finland. Construction started 2005 and it was supposed to be ready in 2009… they are still b
by juahan 5y ago
Well, currently the French are buildin a new nuclear power plant in Finland. Construction started 2005 and it was supposed to be ready in 2009… they are still building it and _maybe_ next year it finally will be connected to the grid. So 17 years give or take.
- pyrale 5y agoFrance lost lots of construction/industrial knowledge wrt nuclear plants. It's not very surprising that new models built by inexperienced companies end up being over budget and schedule. I wouldn't surprised for Hinkley point C to also have such issues. What I would like to know is whether the amount of issues is significantly reduced compared to Flamanville and Olkiluoto. That would be a good indication about whether the design is faulty, or whether it's the industry having teething issues.