For very long distance power transmission, losses primarily depend on voltage and AC>DC>AC conversion efficiency which have both been increasing. China just co
by Retric 5y ago
For very long distance power transmission, losses primarily depend on voltage and AC>DC>AC conversion efficiency which have both been increasing. China just completed a 3,300 km (2,100 mi) 1,100 kV line capable of sending 12 GW at the cost of 5.9 Billion dollars.
Over 1500km you can keep losses under 10%, but building infrastructure isn’t free. East to West links tend to work better because you can time shift demand and thus build fewer power plants.