This is actually being done in France: Construction on a new reactor, Flamanville 3, began on 4 December 2007.[4] The new unit is an Areva European Pressurized
by the_why_of_y 5y ago
This is actually being done in France:
Construction on a new reactor, Flamanville 3, began on 4 December 2007.[4] The new unit is an Areva European Pressurized Reactor type and is planned to have a nameplate capacity of 1,650 MWe. EDF estimated the cost at €3.3 billion[4] and stated it would start commercial operations in 2012, after construction lasting 54 months.[5] The latest cost estimate (July 2020) is at €19.1 billion, with commissioning planned tentatively at the end of 2022.
https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plant https://en.wikipedia.org/wiki/Flamanville_Nuclear_Power_Plan...