Guide to Software Project Estimation
- xcambar 5y agoI am and always will be skeptical about software estimation. I am even more skeptical about the promises of software evaluation methods. But what I am the most skeptical about is teams avoiding software estimation altogether because they share the two skepticisms above.
- commandlinefan 5y ago> avoiding software estimation altogether because they share the two skepticisms above Well, to put your mind at ease, I don't avoid software estimation because I share your skepticisms (although I do), I avoid it because I've observed that it's a complete waste of time. Nobody, at least never in my 30-year career, has ever asked for an honest estimate of how long it would take to produce a software product. What they have asked for is somebody to agree that the time that they have budgeted will be enough for the (vague, still being defined and still to be defined even beyond the timeline) software project and take the "blame" when it inevitably doesn't.
- tupac_speedrap 5y agoYep, every story pointing session is basically just think of a Fibonacci number and round it up. Finishing early makes your scrum master leave you alone but finishing late makes you and your team look bad and "unagile" and then you get even less done next sprint because you are stuck in meetings. The scrum master always wins because nobody is ever doing enough Agile.
- xcambar 5y agoI agree. > somebody to agree that the time that they have budgeted will be enough for the [...] software project For me, that's still software estimation.
- gilbetron 5y agoNothing interesting in the article at all, I have no idea why it is on the front page of HN. As usual with software estimation, unless you've read this paper: http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.19.344 http://citeseerx.ist.psu.edu/viewdoc/summary?doi=10.1.1.19.3... and have a thoughtful response to it (of which I've read some solid ones), I've very little interest in hearing what you have to say about software estimation.
- diiq 5y ago1) The big if is written out in the abstract -- "if it is accepted that algorithmic complexity is an appropriate definition of the complexity of a programming project." Relating algorithmic complexity to "how long software takes to write" seems, to me, to ignore that the vast majority of my time as a developer is spent discovering and communicating requirements, handling human questions, not writing novel code. The conclusion touches on this, but ignores it. 2) Even if you accept that "if", this is like a halting-problem proof. Fine; it is impossible to estimate the complexity of ALL software. That does not mean that it's useless to quantify the complexity of software in limited but well-behaved problem spaces. How much of any commercial project is actually spent working on the cutting edge of computer science, facing complete unknowns? An estimate being wrong occasionally is worth most estimates being mostly right. 3) Why do you consider a 20 year old paper that's only been cited 16 times to be critical reading about estimation, when a vast body of research in forecasting exists, written by people who have measurements of the accuracy of estimates to base their theoretical models on?
- gilbetron 5y ago> 3) Why do you consider a 20 year old paper that's only been cited 16 times to be critical reading about estimation, when a vast body of research in forecasting exists, written by people who have measurements of the accuracy of estimates to base their theoretical models on? Have some links to this vast body? I've encountered very few over the years that actually qualify as "science" as much of it is fake or close to fake. http://shape-of-code.coding-guidelines.com/2021/01/17/software-effort-estimation-is-mostly-fake-research/ http://shape-of-code.coding-guidelines.com/2021/01/17/softwa...
- nicholasjarr 5y agoNever been good at estimation. Software Estimation from Steve McConnell is in my reading list for a long time now. From the little I have seen from it, it look good (I already read Code Complete from him and recommend it). Do you guys have any tips for estimation?
- qznc 5y agoSecond McConnell. It is a great reference for all kinds of estimations around software development. That is also its downside. It is a reference. Not a textbook to learn things in a pedagogical structure.
- nicholasjarr 5y agoYeah. I notice this when I tried to read it the last time. I was expecting something more like Code Complete. I don't know, maybe it is the subject: code is way more interesting than estimation :)
- stronglikedan 5y ago> Do you guys have any tips for estimation? Stick to your guns when Sales tries to get you to change your estimate (and they will). Tell them they can discount the project, or change any other variable they need to satisfy the customer, but don't ever let them touch the time estimate. Not really a tip for making the time estimate, but keep your ass covered once you do.
- okl 5y agoRead that damn book :D It's a treasure trove of information, not only for estimating software projects! For example, learning to differentiate between estimate, target/goal, and commitment. Personally, I'm often dumbfounded that folks still use planning poker when there are so many more reliable methods as discussed in the book, e.g., wideband Delphi.
- diiq 5y agoMcConnell's 50/90 approach makes a big difference in my opinion because it lets you encode your uncertainty. The extra math means you don't need to be good at estimation as long as you know roughly how bad you are at it. If that seems like too much effort, I also run quotes.vistimo.com , which takes a similarly (if slightly more advanced) statistical approach, but does all the math for you.
- automatic6131 5y agoI have no opinion on the content of the article, because light grey on white is barely readable, and it would require far too much energy to read.
- seph-reed 5y agoI got pretty decent at software estimation at my last job. I would spend an entire day "pre-programming" everything in my head, estimating the length of each little chunk, adding them up, then multiply by ~2. It worked for me. But I still would never trust the estimates.
- d6ba56c039d9 5y agoAnother angle. 'How long did a project this size take last time?'. As an aside, years ago I worked at a company that did thorough (and inaccurate) bottom-up schedules. I got dinged for not using quarter hour accuracy in the various task estimates.
- p0nce 5y agoInstead of 2: Multiply by π for new kind of projects. Multiply by φ for known projects.
- zoomablemind 5y agoToo often the software project estimates are driven by some external constraints, not much by the understanding of the effort or complexity. It's either some existing deadline or reporting/sales cycle, some budget caps, like in grant proposals, or some promises already made by/to 'important people', or some fear of 'small people' to underdeliver etc. The estimation would all be fine if all involved people shared the same goal and responsibility. I find it practical to split the desired outcome which needs an estimate into two variants: 1) the most desired/promised/advertized and 2) an at-least viable variant. If noone can see the second variant, its viability and the effort it needs, then some details or skill force are clearly missing. If the second variant is estimatable, then the estimate could be used as a basis in dealing with the external constraints. If the devs are saying that in a given timeframe they can see a prototype done at least and you're fine with that, then no one should be damned if that pans out just to be the case. So it has to be clear from the beginning if it's at all acceptable to put such variant/prototype into production.
- diego_moita 5y agoJust one more consultant doing "branding". What causes estimates to fail are the unknowns: unavoidable surprises when implementing something new, unexpected change in requirements, etc. It would be easy to have accurate estimates if there were no unknowns. But every innovative project must always be a march to unknown territory.
- deleted 5y ago[deleted]