The importance of redundancy and backup alternatives in any major project: "It is worth remembering too, of course, that the F-35 enterprise almost had an alte
by 1cvmask 5y ago
The importance of redundancy and backup alternatives in any major project:
"It is worth remembering too, of course, that the F-35 enterprise almost had an alternative engine to the F135. However, the General Electric/Rolls-Royce F136 turbofan was deemed to be an unnecessary expense and was eventually canceled in 2011, when the project was over 80 percent complete. With the benefit of hindsight, it can well be imagined that an alternative source of engines would be very valuable right now."
- tonyedgecombe 5y agoPerhaps that would have just made it even more expensive, like these projects that want to abstract away the database just inches the customer wants to switch from SQL Server to Oracle.