Dynetics submitted the highest bid, but it looks like their bid couldn't have one at any price. However, notwithstanding these aforementioned positive attrib
by handol 5y ago
Dynetics submitted the highest bid, but it looks like their bid couldn't have one at any price.
However, notwithstanding these aforementioned positive attributes, I find that Dynetics’ technical approach suffered from a number of serious drawbacks, and I concur with the SEP’s conclusion that these drawbacks meaningfully increase the risk to Dynetics’ successful performance of this contract. Of particular concern is the significant weakness within Dynetics’ proposal under Technical Area of Focus 1, Technical Design Concept, due to the SEP’s finding that Dynetics’ current mass estimate for its DAE far exceeds its current mass allocation; plainly stated, Dynetics’ proposal evidences a substantial negative mass allocation.
https://www.nasa.gov/sites/default/files/atoms/files/option-a-source-selection-statement-final.pdf https://www.nasa.gov/sites/default/files/atoms/files/option-...