Coming from a Supply Chain function in aerospace, I have to agree and disagree. 2 months of stock are somewhere around a turn rate from 4-6. A region some aeros
by hef19898 6y ago
Coming from a Supply Chain function in aerospace, I have to agree and disagree. 2 months of stock are somewhere around a turn rate from 4-6. A region some aerospace companies can only dream of.
The problems are, that they stock to much of some parts and not enough from others. That problems gets worse when programs reach end of life, obsolescence is a severe problem then.
Most of the demand fluctuations in aerospace, less so for spares, is home made. Delivery lead times and production lead times are so long, that done right, fluctuations are mainly a problem for long lead time items. And that is manageable.
- Guest42 6y agoI meant 2 months more as a floor across a majority of items(and it’s been a long time since then so there’s a certain amount of rounding). Production wanted to eliminate shortages whereas executives and accountants wanted to optimize turn rates while claiming to care about shortages. Overall, each of the projects had around 2000 unique parts (at least for what this particular plant was making). Occasionally, newer contracts would get a much higher prioritization and could grab parts (and employees) from older projects. Another scenario that would lead to extra demand was having test failures on a project that was nearing design freeze. I ended up changing industries to financial services, but will always have a deep respect and appreciation for what went into those projects.
- hef19898 6y agoThe funny thing is, that aiming for inventory levels, or certain levels across the board, can increase the likelihood of shortages. Higher stock means larger production lots and longer lead times. If for some reason your planned production / procurement doesn't match demand, almost a certainty with large production runs, one part cart run out of stock. And the large production runs make replenishment of this part difficult.
- Guest42 6y agoIt was a very fun game that required knowing the capacity of each supplier and their suppliers as well. The sales orders had to get matched up with airplanes and sometimes the planes would have shortages that would then instantly changes years' worth of scheduling. Overall I felt like there were a number of good strategies but that sometimes the strategizing interfered with the execution. Peoples tenure and the projects they went through often influenced their notion of ideal. By the time I started getting comfortable understanding these things, it was time to get a new job.
- cptskippy 6y ago> The problems are, that they stock to much of some parts and not enough from others. Is there a reason for that? I would imagine they'd have actuarials telling them exactly how much of each thing they need to produce a thing, as well as failure rates.
- hef19898 6y agoInventory management is hard, and one of the main tasks of Supply Chain Management. In the end, I have yet to see a formula, algorithm or model that calculates stock levels that isn't over shooting at a factor of 2, either way. In the end, it is the tram and person responsible for inventory planning and placing production / purchase orders that set, directly and indirectly, inventory levels. In some cases 2 months maybe just right. In other cases it maybe 1 month to much, in again other cases not close to enough. And that can change over time. As a rule of thumb, you don't want inventory. It makes an operation inflexible and fat. You need it so. Figuring that out is the task planners and supply chain managers. Some orgs are better at that then others.