> However, there has not been any new generation capacity since 1994. That's not true. Majuba Power Station was commissioned between 1006 and 2001, although pl
by igitur 6y ago
> However, there has not been any new generation capacity since 1994.
That's not true. Majuba Power Station was commissioned between 1006 and 2001, although planning started in the Apartheid era. Gourikwa Power Station and Newcastle Cogeneration Plant were commissioned in 2007.
There are a few wind farms built after 2001: Hopefield, Coega, Darling, Klipheuwel, Dassiesklip Wind Energy Facility and Jeffreys Bay.
And solar: Kalkbult, Mulilo Renewable Energy Solar PV Prieska, De Aar Solar PV, Mulilo Renewable Energy Solar PV De Aar, SA Mainstream Renewable Power Droogfontein, Letsatsi Solar Park, Lesedi PV Project, Kathu Solar Energy Facility 1, Sishen Solar Facility and the Jasper Solar Energy Project.
But these were not enough to keep up with the demand.
- igitur 6y agoMajuba Power Station was commissioned between 1996* and 2001